Building hand-over date falling behind due to high moisture content in the floor screed and associated slow drying caused by inclement weather conditions and building not being “air tight” resulting in ;-
1. Floor screed too wet to lay new vinyl flooring though out new building of 3,500 m2.
2. Delay (by M & E Contractor) of newly installed boiler & heating services not ready in time to assist drying.
(The client previously used Aggreko with IDF heaters with lots of ducting throughout building “which were expensive and took a very long time”).
Dry floor screed to four designated “phases” of the building each at different times and speeds to be in line with estimated floor layers work.
Supply two Watkins Hire MBR 250kw mobile boilers & GSM monitored 3000-litre fuel tanks c/w pipe work and appropriate tee manifolds to the designated newly installed under floor heating system.
WHL past and current under floor heating projects offer their customers a “one stop” drying solution particularly where the new boiler plant has yet to be commissioned and newly laid flooring needs to be carefully dried.
Specialist hire director Andy Ellis visited the Basildon site and discussed the application with site Mangers Quantity Surveyor.
WHL’s unique global satellite monitoring (GSM) telemetry system fitted to their equipment also helped the builder to maintain continuity of heating throughout the hire and eliminated any down time and associated problems involving additional refuelling deliveries or possible equipment breakdowns.