Friday, February 27, 2009

Floor drying




Heating boiler hire project application
Building hand-over date falling behind due to high moisture content in the floor screed and associated slow drying caused by inclement weather conditions and building not being “air tight” resulting in ;-
1. Floor screed too wet to lay new vinyl flooring though out new building of 3,500 m2.
2. Delay (by M & E Contractor) of newly installed boiler & heating services not ready in time to assist drying.
(The client previously used Aggreko with IDF heaters with lots of ducting throughout building “which were expensive and took a very long time”).


Application requirement
Dry floor screed to four designated “phases” of the building each at different times and speeds to be in line with estimated floor layers work.


The Solution
Supply two Watkins Hire MBR 250kw mobile boilers & GSM monitored 3000-litre fuel tanks c/w pipe work and appropriate tee manifolds to the designated newly installed under floor heating system.


Following the recent inclement weather conditions, Watkins Hire Ltd were asked to provide a solution to a major national building contractors problem of appropriately drying out 3,500 m2 of floor screed without causing any associated damage to the floor.
WHL past and current under floor heating projects offer their customers a “one stop” drying solution particularly where the new boiler plant has yet to be commissioned and newly laid flooring needs to be carefully dried.
Specialist hire director Andy Ellis visited the Basildon site and discussed the application with site Mangers Quantity Surveyor.


Andrews 23 year Temperature control hire application experience involving boilers and chillers helped advise the building contractors to utilise the existing under floor heating system connected to two WHL 250kw LPHW boilers.


“The builder required four different floor areas to be dried at different drying rates and times to meet the proposed floor layers programme of works” said WHL’s Andy Ellis, and the process needed well controlled temperature gradients to ensure the drying did not cause other problems.


Each hire boiler was connected to a total of 19 newly installed under floor heating manifolds with low temperature hot water circulating through the temporary pipe work installed by WHL engineers.



WHL’s unique global satellite monitoring (GSM) telemetry system fitted to their equipment also helped the builder to maintain continuity of heating throughout the hire and eliminated any down time and associated problems involving additional refuelling deliveries or possible equipment breakdowns.

Boiler Hire Keeps Christmas Mail Sorting Open

Watkins Boiler Hire supplied a 500kw of Boiler for temporary heating for a temporary Christmas mail sorting office near London. Watkins Boiler Hire maintained heating with a 500kW Boiler and five off 100kw air handlers connected by flexible pipework.


The Facilities Manager said


"Watkins Hire were on site within 2 hours of us placing the enquiry, their specialist sales manager completed his survey and had a solution to our problem whilst still in our office. When all of the options were considered we made the decision to place the contract with Watkins Hire. The operation of the temporary boiler plant room left us with no hesitation that this was the right piece of equipment for the job. Along with the equipment being available and Watkins Hire offering a Web based fuel management service, it leaves us with piece of mind that the staff will have no complaints about being cold."


For more information on our products and services visit www.watkinshire.co.uk